The Stand Alone Growth Project is a theoretical project to undertake only the works necessary to provide for the incoming growth demands on a Stand Alone basis (i.e. they may not use any existing infrastructure).
|
The Stand Alone Growth Project would be considered as if the growth / development community had established the new facility on their land to meet the Level of Service requirements of the growth community. |
|
If the asset would require land for its establishment the cost of that land must be included in the scope and cost of the Stand Alone Growth Project. |
Recognising that it may not be prudent for a community to be provided with a plethora of stand alone projects a 'system efficiency premium' is applied; this is currently accepted to be 10%. This premium represents acknowledgment that acceptance of numbers of developer implemented schemes will present a less efficient network with the added implications of higher operation, management and maintenance costs.
|
Where the the Stand Alone Growth Share is less than the calculated Growth Share Cost, the difference is identified as an Unallocated Cost share. |
Select the required Outcome from the drop down list at the top of the screen.

Projects with multiple Outcomes will require data entry for each individual Outcome.

Field |
Description |
|
|---|---|---|
discussion |
Commentary to support the Growth figures. |
|
Components: |
|
|
|
item |
A number that identifies the component item. |
|
|
Will be automatically generated, but can be modified. |
|
description |
A brief description of the Growth component. |
|
unit |
Component unit of measure. |
|
|
Can be blank. |
|
quantity |
The quantity of this component. |
|
rate |
The rate for 1 component unit. |
|
amount |
The calculated component unit cost. |
|
|
quantity * rate |
stand alone growth cost |
Calculated as the sum of the component costs. |
|
cap on growth cost share |
Calculated as the stand alone growth share *(1+ 10%) |
|
The growth screen is not a compulsory screen in the cost allocation process. i.e. not completing this screen would not make the project cost allocation incomplete for DC calculation.